l. The radial skip of the
equipment spinning axle shall be< =0.04mm. The axial flee |
| |
shall be <=0.1mm |
 |
2. Keep the seat and the chamber
sealed clean during the installation, Clean the |
| |
sealing fittings and check for
perfect sealing surfaces. Keep the sealed positions away from
the impurity and dust. |
 |
3.Any stroke, collision and
knocking are strictly forbidden to avoid the failure of the |
| |
seals due to the damage by
above-mentioned rough operations. |
 |
4.Put some clean oil (recommend
to use soap water ) on the surfaces which are in |
| |
contact with the secondary seals
. |
 |
5. Give a uniform force to the
screws while tightening them up during the |
| |
installation of the gland to
ensure verticality of the ring surface to the axis of the
axle. |
 |
6.Push the rotating ring with
your hand after installation and make it possible to |
| |
move freely on the axle and
elastic laceration degree. |
 |
7. Turn the spinning axle by the
hand wheel after installation to make sure that the |
| |
axle spins with neither fatigue
nor extra ease. |
 |
8. The equipment shall be filled
with mediums before it is put into operation so as |
| |
to avoid the failure of the
seals due to dry friction. |
 |
9. Corresponding measures, such
as washing ,filtering and cooling shall be taken |
|
when the temperature of the
mediums that may be easily crystallized or granulated |
|
exceeds 80°C. As to the other
auxiliary systems, see the relevant standards on the |
|
mechanical seal. |
 |
10. Should have the shaft run by
hand after stopping running for a long time , which |
|
can prevent mechanical seals
from damage due to the adsorb of the sealing |
| |
faces or the clog of the
seals. |